AUSTIN-BERGSTROM INTERNATIONAL AIRPORT 
CONSOLIDATED RENTAL CAR FACILITY

Project Update: April 2015

This southeast view from March 19 shows the ABIA Consolidated Rental Car Facility nearing substantial completion.

DESIGN AND CONSTRUCTION UPDATE

With substantial completion of the main building on the horizon, construction at the Austin-Bergstom International Airport Consolidated Rental Car Facility is steady. Pfeffer Development has the project on track and within budget to be completed by the delivery date of September 1 for all tenant work for the rental car companies.

Central Texas Reinforcement (CTR), the reinforcing installer/supplier, is installing miscellaneous column reinforcing and barrier cables throughout the project. To date, CTR has installed over 5,979 tons of reinforcing steel. CTR has also placed over 644 tons of post tensioning tendons.

APAC-Texas Inc., the concrete supplier, along with Austin Commercial has placed approximately 77,488 CYDS of concrete material for foundations, columns, slab on grade and elevated  deck to date.

Young and Pratt, the plumbing and HVAC subcontractor, has installed all of the base building AC units that serve outlying rooms as well as sinks and toilets in all of the restrooms. Ductwork and plumbing rough-in is currently being installed throughout the tenant space. Young and Pratt is gearing up to begin startup as soon as permanent power is available to the various systems. Also, once permanent water is established to the site, a chlorination of all of the piping will be done prior to building turnover.

Schmidt Electric, the electrical subcontractor, has coordinated with Austin Energy this past month to have permanent power brought to the transformer. Once the meter is set, permanent power can be turned on in phases throughout the site and temporary power will be turned off. 

Patriot Erectors, the steel subcontractor, has fabricated and erected the bent beams at the pedestrian walkway from which the artwork and overhead steel will be hung. Patriot Erectors has also erected the steel framing for the wire mesh at the stair towers. Installation of the vertical support cables and support steel for the wire mesh at the west façade is also complete.

Texas Roofing, the roofing subcontractor, has completed the roofing installation on the Customer Service Building (CSB) as well as the high roof canopy. Crews are now working on the low canopies and will begin the toll plaza roof soon. Once those are completed, they will be moving to install the pedestrian walkway canopies.

Avery’s Lawn Care, the landscape and irrigation subcontractor, has completed a majority of the irrigation throughout the job site and continues to make progress in areas as they become available. Avery's Lawn Care has also made significant progress with restoring the landscape spine on the west side of the building. A significant amount of topsoil has been spread throughout the available areas as well by Avery's Lawn Care.
 

Project Summary

Air travelers to Austin will soon have access to a new Consolidated Rental Car Facility at the Austin-Bergstrom International Airport. The $155.5 million project commenced in the spring of 2013 and is scheduled for completion in the fall of 2015.

In addition to the rental car facility, the project will expand public parking at the airport. Covered parking will replace the uncovered parking spaces on lot A, and space on the third floor of the existing garage will be converted to public parking, resulting in an increase of approximately 900 covered short-term spaces. 

Visitors will access the facility from the terminal by a pedestrian walkway to the existing garage and an elevated pedestrian bridge from the garage to the rental car center. The pathway will be enhanced with dramatic artwork by Michael Singer, commissioned through the City of Austin Art in Public Places Program.



 

This photo from March 18 portrays a unique perspective of the toll plazas.

Crews can be seen here on March 17 focusing on the west helix as one of the last remaining substantial sections of the project.

SCHEDULE

Groundbreaking: Spring 2013
Exit Plaza Switchover: Summer 2013
First concrete pour (piers): Fall 2013
Topping Out: Fall 2014
Opening Date: September 1, 2015 
 

PROJECT FACTS

•  Located on eastern half of Lot A
•  1.6 million square feet facility
•  Quick Turnaround Areas include:
     - 12 car wash bays
     -  48 fuel/vacuum/window washer
        fluid and air stations
•  Reduction in vehicle exhaust will lower
   carbon dioxide emissions 411.7 tons/yr.

                   

PROJECT TEAM

Owner: Austin-Bergstrom International Airport
Master Lessee: Austin CONRAC, LLC
Developer: Pfeffer Development
Design-Builder: Austin Commercial 
Architect: Demattei Wong Architecture
Facility Users: Ace, Advantage, Alamo, Avis, Budget, Dollar, Enterprise, Hertz, National, Thrifty

Project Update Provided by:
Pfeffer Development, LLC
Bob O’Neill, PE
Email: boneill@pfefferdevelopment.com
Phone: 907.646.4644

                   

Copyright © 2015 Pfeffer Development, LLC, All rights reserved.


unsubscribe from this list    update subscription preferences